Monday, July 30, 2012
...and now it's time for a break.
It's been one thing after another at the office, with two big projects in very needy stages. Gestalt's Uber MOB is in CA, so every question is urgent; St. Ermahgerd is just starting schematic design, so we're making fast and crucial decisions regarding how the building should look and how the departments should be arranged and laid out. I've been moving so fast and furious lately that I've actually been getting in Howie's grill, being defensive and reflexively irate. Kitty's appearance in the Mile High gives me an opportunity to take a Monday off and bring my blood pressure down a little bit.
Breathe, snuggle kittehs, flip through Elle Decor, and rest.
Monday, January 2, 2012
Next on The Life of Pixie: Drama, rumors, and a little better pat on the back, Part 1
Thursday, October 20, 2011
Scenes from a project, Part 1
Pixie: Well, maybe two. Depends on what you [gestures at Gestalt Mgrs 1 and 2] want. Do you want me to see if it can really work, or do we just want to be able to say 'yeah we tried but it's not gonna work' to the radiologists?
Wednesday, October 12, 2011
The deadline: close, but no cigar.
Thursday, August 18, 2011
Next on Dr. Phil: architects that rarely draw...but can they sketch??
- SD - schematic design, where we figure out basically where which rooms go where in the departments, what spaces are needed, what spaces we forgot to account for (figuring out where the departments go in the building is also done during SDs, but on a project this size it was part of a separate pre-SD phase)
- DD - design development, where we confirm room locations and then being working out how the building looks, inside and out. We also confirm with the building's users where the cabinets and sinks are, what equipment goes where, and so on.
- CD - construction documents, where we start drawing all the little details in earnest and really work through how all the building's systems work together. (Some of this coordination happens during DDs as well, but now it's Gotta Be Done.)
Saturday, June 25, 2011
Relentless
Monday, April 4, 2011
And now, time to hold our breath
- are the construction materials the kinds that they, system-wide, know how to clean and maintain?
- are the materials used in the building the best-priced ones that can also do the job?
- are the rooms and spaces in the project too large or too small to deliver good care?
- does the project account for expansion in the near and not-so-near future? Does it also account for any upgrades or small renovations (e.g., adding extra offices, building out more exam rooms or ORs)?
- does the project make the best use of the site, views, etc.?
- does the project have everything it was programmed to have (e.g., ten pre-op bays for five ORs; one doctor's office for every two exam rooms) that will allow them to deliver cost-effective care?
- and finally, is it under budget, and can it be built on schedule?
Thursday, March 24, 2011
Someone call Glenn Frey, because the heat is on.
Thursday, February 10, 2011
Architectural grocery lists
Monday, February 7, 2011
Everybody wants to rule the world
Monday, January 24, 2011
Hooray! The internet's back!
Monday, January 10, 2011
Wish in one hand, draw with the other
Tuesday, January 4, 2011
...aaand we're back.
Monday, November 22, 2010
Thanksgiving...and not a moment too soon
Thursday, November 11, 2010
Who watches the Watchmen? Part 2 of 2
Monday, October 25, 2010
Contractors: the older brothers I never had, the cool kids I never got to hang out with
I don’t know why I like contractors so much. I mean, technically I should like them because they build the things I draw, and some of them build those things very well. To be fair, I don’t think I’ve ever met a bad contractor (and I’ve met very few bad subcontractors)—since I do healthcare and other large-scale commercial projects, I think that’s helped to separate the crap from the mulch*. But I just like being around them—I feel like I’m being allowed into an exclusive club, or even being allowed to observe a completely different species in its natural habitat.
We sit down around a folding table in the construction trailer at 7:30am, ready to start our OAC**. I have to do a job walk afterwards, so I’m wearing pants and closed-toe shoes, but I’m still dressed like I have a white-collar job. The contractors with whom I’m working on the Gestalt main floor renovation, Glasnost Construction, range in ages from late-20s to mid-50s. Leaning on the table with wide, tanned forearms, looking intensely at the meeting minutes and each other, Gestalt baseball caps covering the hair that’s been plastered down by hard hats for almost three hours already***, the various superintendents, foremen, and project engineers look like giants compared to me. Their XXL t-shirts stretched over barrel chests and chiseled biceps and 36- to 38-inch inseam jeans lapping over size-14 Redwing work boots belie a seemingly-unspoken hiring rule at Glasnost: you must be at least 6’-0” tall and 240 lbs to run a project. I’m not even kidding: the shortest contractor on my jobsite is the project engineer, Vlad, and he’s 6’-0” tall and in his early 30s, while the other three are 6’-2” (Boris, late 40s), 6’-5” (Ivan, early 40s), and 6’-7” (Yuri, late 20s). (The Glasnost project manager, Darko, is maybe 5’-9” and in his 50s, but he’s worthy of his own post, that guy.)
The size and cultural difference is most noticeable in the field. After the OAC, we walk around the parts of the main floor of the Bierstadt building under renovation. As we approach the job site, Yuri hands me a pink hard hat. “It’s not a statement about you, Pixie,” he says. “It’s just the only way we can guarantee that none of the other guys will wear your hardhat and get their head funk in it.” I tighten it down onto my head and walk into what looks like a street scene in Iraq—fluorescent lights hang crookedly while sparks fly from someone welding support steel for a coiling door across the room. I can look straight up to see wires, ducts, and even the underside of the next concrete floor above us. As I lift my leg to step over some construction debris, Ivan steps down onto it to flatten it out so I don’t have to step so far. I ask to look into a portion of the exterior wall that’s about eight feet above the floor, and someone produces a ladder. As I climb up, two large men hold the bottom—it’s overkill for stabilizing a ladder for someone barely over 120 lbs, but it’s very kind: don’t let the little architect fall. As Yuri and I take measurements of an undocumented fire extinguisher cabinet (we’ll have it deported the next day), a drywaller across the room lets loose with a string of F-bombs. Boris takes two steps towards the man and silences him with an icy glare: watch your mouth, there’s a lady present.
It’s educational and downright fun sometimes to hang out with contractors. You listen to them talk about past projects and problems they had on those projects and how they solved them. You even hear them describe, sometimes unintentionally, what makes a good carpenter/plumber/electrician/painter/whatever. You hear them gossip about other clients, even people they haven’t worked for. Turns out my Glasnost crew at Gestalt have friends who worked at MHRC back when I was working with Squidwort, and they heard what I saw firsthand—a research clinic with a lot of money and the entire management eating bowls full of crazy for breakfast every morning. I’ve found overall that the best way to work with contractors is not to assume that they’re always right or always wrong. They’ve seen some stuff, and you’ve seen some stuff, and between the two or three or twelve of you, you can find a way to solve anything.
*I hesitate to say the men from the boys, as I’ve met some good women contractors and carpenters. They’re few and far between in commercial work, but they do exist. My mom is one of them.
**“OAC” is short for “Owner-Architect-Contractor meeting”, which are held periodically to discuss progress on a project, bring up present or future concerns, discuss the best solution for intractable problems, and so on.
***In renovation projects where the building has to remain operational, contractors will often start work very early in the morning to get noisy stuff out of the way, like core drilling. Plus, starting early in the morning allows them extra time in the afternoon to fix something in case there’s a problem.